New construction of one and two family homes
The following is information to be used for the planning prior to the issuance of a building permit.
Building codes
- 2006 International Building Code, including supplements
- 2006 International Residential Code, including supplements
- 2006 International Mechanical Code, including supplements
- 2006 International Property Maintenance Code, including supplements
- 2009 International Energy Conservation Code, including supplements
- 2006 International Fuel Gas Code, including supplements
- 2005 National Electric Code, including supplements
- 2006 International Fire Code, including supplements
- Latest Illinois Accessibility Code, including supplements
- 2007 NFPA 13 Fire Sprinkler Code, including supplements
- 2007 NFPA 72 Fire Alarm Code, including supplements
- 2006 NFPA 101 Life Safety Code, including supplements
- Latest Illinois Plumbing Code including supplements.
Two complete sets of plans shall be submitted for review to include:
- Site plan
- Grading plan
- Footing and foundation
- First floor
- Second floor
- Floor framing
- Roof framing
- Quarter and half sections indicating details not shown on plans
- Floor and roof truss specifications
- Window and door schedule
- Front, rear and side elevations
- Light and ventilation schedule
Foundation and basement
- Footing sizes
- Footing for columns: size and placement
- Size of basement foundation
- Basement windows location
- Footing drains and sump
- Girder beam
- Size and type of column for girder beam
- Sill size and anchor bolt sequence
Stairways
- Maximum riser height: 7 3/4 inches
- Minimum tread depth: 10 inches, nose to nose
- Clearance for headroom: 6 feet - 8 inches
- Height and spacing of handrails and guardrails
- Stair detail required
Framing
- Floor joist and decking - size, grade, species, spacing
- Floor truss - engineers specifications
- Interior wall covering - type
- Exterior sheeting and wall covering
- Wall bracing
- Fire stopping including soffits, stairs etc.
- Exits and landings
Roof
- Rafters - size, species, grade, spacing
- Truss - stamped/sealed certificates
- Shingles - weight and type
- Pitch
- Sheeting - type
- Ceiling joists - size, species, grade, spacing
- Attic ventilation schedule
Insulation
- R-values of ceiling and exterior walls
Fireplace
- Factory built-size, type and placement
- Masonry-size, type and placement
- Chimney-size, type, model, height above roof
Electric
- Location of light fixtures
- Location of receptacles
- G.F.I locations
- Electric service size and location
- Location of smoke detectors
Call for an Inspection 24 hours before:
- Footings are poured.
- Foundation is backfilled.
- Concrete slabs are poured, i.e basements, sidewalks, garages, etc.
- Interior and exterior walls are insulated and drywalled. All mechanical, electrical and plumbing runs must be complete.
- After insulation installation, before drywall.
- After water and sewer connections are made, before backfilling
- Final inspection made prior to occupancy.
|